Vattenfall installs its third large battery system in Sweden

15. OKT 2024 10.50
Energilagring

In the forests northwest of the small town of Bruzaholm in Eksjö municipality in Sweden, Vattenfall is currently constructing a large battery storage facility, which will be built in connection with the Bruzaholm wind farm, which will consist of 21 Siemens Gamesa turbines, which will be ready in spring 2025.

The battery system will consist of 60 battery modules with a total output of 38 MW and with an energy storage capacity of 38 MWh, the battery will help maintain the balance of the electricity system and contribute to reduced fluctuations in electricity prices.

Installation of the battery system will begin in October and be completed before the turn of the year. The facility is expected to be fully operational in September 2025.

amp

Text, graphics, images, sound, and other content on this website are protected under copyright law. DK Medier reserves all rights to the content, including the right to exploit the content for the purpose of text and data mining, cf. Section 11b of the Copyright Act and Article 4 of the DSM Directive.

Customers with IP agreements/major customer agreements may only share Danish Offshore Industry articles internally for the purpose of handling specific cases. Sharing in connection with specific cases refers to journaling, archiving, or similar uses.

Customers with a personal subscription/login may not share Danish Offshore Industry articles with individuals who do not themselves have a personal subscription to Danish Offshore Industry.

Any deviation from the above requires written consent from DK Medier.

https://www.doi.dk/en/vindkraft/artikel/vattenfall-opstiller-sit-tredje-store-batterisystem-i-sverige

GDPR