Almost 13 of the planned 26 km of electricity cables have now been laid in the ground on the section from Holstebro to the German border, where the work has been particularly affected by difficult ground conditions and rain. The West Coast Link, which will connect the electricity grid from Central Denmark to the border, consists mainly of 400 kV overhead lines, but approximately 26 km will be established as underground cables.
The nine 400 kV and three 150 kV cable sections are distributed in areas with vulnerable nature such as streams, watercourses and plantations. The project has been challenged by flooded fields, difficult soil conditions, archaeological finds, expropriations and consideration for protected animal species.
- It is therefore particularly pleasing that we are now well over halfway through the cable section, as we had so many challenges at the beginning and had to take small pieces at a time. Now we believe and hope that the rest will proceed according to plan, says Sigurdur Mar Bjarnason, senior project manager at Energinet, in a press release.
In the northern part between Endrup and Idomlund, there are now cables in the ground at Omme-Endrup and Sig-Skonager, while the sleeve work continues. At Skjern Å, 8 out of 12 underbores have been completed. In the southern part between Endrup and the border, several sections have been completed, and new ones are expected to be completed during 2025. The entire cable laying is expected to be ready for commissioning in the spring of 2026.
amp
Text, graphics, images, sound, and other content on this website are protected under copyright law. DK Medier reserves all rights to the content, including the right to exploit the content for the purpose of text and data mining, cf. Section 11b of the Copyright Act and Article 4 of the DSM Directive.
Customers with IP agreements/major customer agreements may only share Danish Offshore Industry articles internally for the purpose of handling specific cases. Sharing in connection with specific cases refers to journaling, archiving, or similar uses.
Customers with a personal subscription/login may not share Danish Offshore Industry articles with individuals who do not themselves have a personal subscription to Danish Offshore Industry.
Any deviation from the above requires written consent from DK Medier.