Abandoned district heating project costs almost DKK 10 million.

29. SEP 2025 11.00
Energi
Økonomi

DRAGØR: It was a short adventure for Dragør Fjernvarme. The company was supposed to achieve a district heating connection of 65 percent in 2024 in order to receive a municipal loan guarantee, but that never happened. Now the shutdown is costing the municipality millions, writes Klimamonitor.

This also means that Dragør Municipality must pay 9.6 million DKK to close the company, among other things covered by a cash draw of 5.6 million DKK.

- I am both annoyed and saddened on behalf of the 35 percent who had agreed to district heating. But now we have to decide on the liquidation of the company, and I would just like to recommend the Economic Committee's recommendation, says Helle Barth, member of the municipal council for the Liberal Party.

ap

Text, graphics, images, sound, and other content on this website are protected under copyright law. DK Medier reserves all rights to the content, including the right to exploit the content for the purpose of text and data mining, cf. Section 11b of the Copyright Act and Article 4 of the DSM Directive.

Customers with IP agreements/major customer agreements may only share Danish Offshore Industry articles internally for the purpose of handling specific cases. Sharing in connection with specific cases refers to journaling, archiving, or similar uses.

Customers with a personal subscription/login may not share Danish Offshore Industry articles with individuals who do not themselves have a personal subscription to Danish Offshore Industry.

Any deviation from the above requires written consent from DK Medier.

https://www.doi.dk/en/solenergi/artikel/nedlagt-fjernvarmeprojekt-koster-naesten-10-mio-kr

GDPR