PtX project in headwind: The Ramme plant has not delivered a drop after ten months

3. JUL 2025 10.03
Power-to-X
Produktion

In August last year, two ministers and a mayor cut the ribbon on what was called the world's first dynamic 'power-to-ammonia' plant in Ramme near Lemvig. The plant, established by Skovgaard Energy in collaboration with Topsoe and Vestas, was to convert green electricity from the sun and wind into ammonia as a replacement for fossil fuels for ships and aircraft. This is reported by DR.

But ten months later, not a drop of ammonia has yet been produced. The plant in Ramme is not the only PtX project to experience start-up problems. Similar plants in several places in the country have been delayed or scaled down. According to Michael Madsen, head of department for PtX at Green Power Denmark, green hydrogen and green fuels are a new market in its infancy, which makes it challenging to get all the elements to work together.

- In my opinion, there has been a bit too much hype around this technology, says Brian Vad Mathiessen, professor of energy planning at Aalborg University, who believes that we are still in a demonstration phase where experience needs to be gained.

Skovgaard Energy did not want to comment on the matter.

Text, graphics, images, sound, and other content on this website are protected under copyright law. DK Medier reserves all rights to the content, including the right to exploit the content for the purpose of text and data mining, cf. Section 11b of the Copyright Act and Article 4 of the DSM Directive.

Customers with IP agreements/major customer agreements may only share Danish Offshore Industry articles internally for the purpose of handling specific cases. Sharing in connection with specific cases refers to journaling, archiving, or similar uses.

Customers with a personal subscription/login may not share Danish Offshore Industry articles with individuals who do not themselves have a personal subscription to Danish Offshore Industry.

Any deviation from the above requires written consent from DK Medier.

https://www.doi.dk/en/ptx/artikel/ptx-projekt-i-modvind-ramme-anlaegget-har-efter-ti-maaneder-ikke-leveret-en-draabe

GDPR