Energinet completes 150 kV cable between Herning and Videbæk

21 km of underground cable will strengthen the electricity grid and make room for more green power.
27. APR 2026 15.53

Energinet is ready to put voltage on a new 150 kV underground cable between Herning Sydvest and Videbæk. The 21 km long section is the second stage of a larger project that will expand the electricity grid in Central and Western Jutland and make room for more renewable energy and increasing electricity consumption.

The construction work began in the autumn of 2025 and was carried out under difficult conditions with wet terrain, frost and crossing both infrastructure and protected nature. In several places it has required extensive and technically demanding undercutting, Energinet states in a press release.

- It has been a complex construction work, where many considerations had to be combined into a higher unit. We worked in an area with wet terrain, where traditional excavation work has not been possible in several places. At the same time, we have had to cross both roads, watercourses and areas with protected nature - and this has required extensive planning and a number of technically difficult undercutting. The fact that we have come this far in a relatively short time is due to close and constructive cooperation with landowners, municipalities, the Danish Road Directorate and our contractor, Arkil, says Rune Bruun Mosbacher, project manager at Energinet.

Among the largest works was a 325-meter-long underboring under the Vorgod Å and Abild Å rivers. In addition, underborings have been carried out at the Herning Sydvest Højspænjingensstation and under Dronningens Boulevard in Herning in connection with road works on Route 15.

The cable has been tested and ready for operation. The final work with cleanup and restoration is missing, and compensation must be paid to affected landowners before the project is finally completed. The commissioning is also a prerequisite for Energinet to be able to proceed with the plans to dismantle the 150 kV overhead line between Struer and Herning, which is now entering a planning phase.

amp

 
 
 

Text, graphics, images, sound, and other content on this website are protected under copyright law. DK Medier reserves all rights to the content, including the right to exploit the content for the purpose of text and data mining, cf. Section 11b of the Copyright Act and Article 4 of the DSM Directive.

Customers with IP agreements/major customer agreements may only share Danish Offshore Industry articles internally for the purpose of handling specific cases. Sharing in connection with specific cases refers to journaling, archiving, or similar uses.

Customers with a personal subscription/login may not share Danish Offshore Industry articles with individuals who do not themselves have a personal subscription to Danish Offshore Industry.

Any deviation from the above requires written consent from DK Medier.

https://www.doi.dk/en/bess/artikel/energinet-faerdiggoer-150-kv-kabel-mellem-herning-og-videbaek

GDPR